top of page

Etz Efraim building
A second opinion for the project of a house built above 10-14 m of uncontrolled fill, and a solution that financially enabled the execution of the project.
The challenge:
The project entered the execution phase of piling drilling but encountered a problematic soil section consisting of a deep fill that did not enable the implementation of the solution given by the previous consultant.
The solution:
2 execution solutions were given, the first - deep foundation while taking care of the landslides that occur during the execution and the second - stiffening the fill with a network of concrete columns and basing the structure on a barge (raft).
The project was carried out successfully.




bottom of page